This 3-phase project addresses pain points identified by the campus community surrounding the process of updating identity information.
Phase 1 | MyFresnoState Shortcut: Complete!
Phase 2 | Mobile@FresnoState: A dynamic mobile Student Profile in the Fresno State Mobile app creates a personalized digital experience available to students to update their preferred name and pronouns.
Phase 3 | Universal Data Access (API): A generic API endpoint will be available for other campus applications to consume and display someones preferred name on applications that they utilize everyday.
Technologies: Modolabs, Boomi
This project provides technology partnership to Fresno State’s guaranteed admissions program, Bulldog Bound. From the registration process to a dynamic and personalized mobile experience, we continue to innovate and improve the prospective student digital experience.
Technologies: Modolabs, Boomi, Kuali Build, OMNI CMS, CRM
This project is Phase 1 of Mobile@FresnoState redesign and is the first step in reimagining the digital experience and transforming how our campus community engages and interacts with technology.
Technologies: Boomi, Modolabs
This project sees the implementation of mobile notifications via Mobile@FresnoState to enables our campus community to engage in a more personal, meaningful, and targeted way.
Technologies: Boomi, Modolabs
Technology Enhancements
This project transitions the current externally supported calendar to Omni CMS integrated calendar. This digital experience creates a seamless experience for Calendar Masters when creating events and allows the campus community to easily search for campus events.
Technologies: OMNI CMS
This project provides an OnBase integration to other form applications to create custom PDFs that can be stored in OnBase. This integration can be used to automate workflows that require document storage in OnBase.
Technologies: Boomi, OnBase
AY 23-24 Completed Projects
Project | Duration |
---|---|
Phase 1 Campus Applications and Classified Data Inventory | January 2024 - April 2024 |
Financial Services Forms 23-24 | September 2023 - March 2024 |
HR Digitalization of Personnel Files | October 2023 - March 2024 |
Phase 1 Change Control | January 2024 - Feburary 2024 |
Phase 1 Preferred Names and Pronouns | January 2024 - January 2024 |
Digital Document Accessibility Training | February 2023 - February 2024 |
Preferred Names MyFresnoState Shortcut | December 2023 - January 2024 |
Third Attempt | July 2023 - January 2024 |
Ph. 2 Kuali Build Implementation | October 2023 - January 2024 |
Ph.1 Bulldog Bound | April 2023 - September 2023 |
HR Telecommute Agreement in Kuali Build | April 2023 - July 2023 |